Screamin' Eagle

About

Challenges

  • Performnce was below the well’s decline curve using a bypass plunger

  • The well was producing 864 µcf/day with a casing pressure at 730 PSI

  • The cycle times were consistently running around 25 minutes

Results

  • Increase of 184 µcf/day which brought the well to 1,048 µcf/day total and the casing pressure was reduced to 610 PSI

  • The plunger cycle times were reduced by 16%

  • The increase of gas production alone earned the operator around $11,000 more in 30 days

Have a similar problem?

The Screamin' Eagle cut cycle time by 16%, reduced pressure by 120 PSI, and increased production by 184 µcf/day.

For more information about how Well Master can meet your needs, contact us today!

  • Instagram
  • Facebook
  • LinkedIn
  • YouTube
  • TikTok
Return to Home Page

US Corporate Office

+1 (303) 980-0254

info@wellmaster.com

16201 Table Mountain Pkwy Suite 100

Golden, CO 80403

Canada Corporate Office

+1 (780) 539-5037

WMCanada@wellmaster.com

102,11334 89 Avenue

Grande Prairie, AB T8V 5V8

© 2024 Well Master Corporation. All rights reserved.

bottom of page