Challenges
Production from wells needed to be optimized installation of artificial lift
Production, downhole velocities, pressures, & tubing performance curves needed to be analyzed
Tool selection & operational parameter recommendations were needed
Results
71% uplift in gas production and 157% increase in fluid production
Essentially eliminated the operators need to unload wells to tanks & release GHG to atmosphere
More consistent and predictable production declines. Effective artificial lift results in stable, steady, & predictable production
The operator developed their own best practices, which carried forward, they applied to additional wells
Have a similar problem?
Operator found a 71% uplift in gas production and 157% increase in fluid production after installation of the Xcel Jetted Pad.